Home
Somerset progresses vertically
We are pleased to bring you an update from site, where the two tower cranes are now installed and the Golden Sedayu Construction team continues to progress at pace on Somerset.
Two tower cranes signal continued progress at Somerset
We are pleased to bring you an update from site, where the two tower cranes are now installed and the Golden Sedayu Construction team continues to progress at pace on Somerset.
Golden Sedayu introduces Somerset VIPs to in-house construction team
With the tower cranes now installed, it marked a wonderful opportunity to invite buyers and Somerset VIPs to meet Golden Sedayu Construction, the WA-based in-house Golden Sedayu construction arm.
Starting the New Year Strong at Somerset
Golden Sedayu Construction has maintained strong momentum over the festive period, with the successful installation of the tower crane for Somerset East. The erection of the crane marks a key milestone for Burswood Point, signalling the vertical commencement of the first building within the broader 38-hectare masterplanned community.
Somerset construction progress
At the close of 2025, we are pleased to report that the piling is now 100% complete and that the piling contractor has now demobilised from site. This is a major milestone for the project as Golden Sedayu moves forward with progress on the individual towers.
Golden Sedayu accelerates Burswood Point vision with Local Development Plan lodged for mixed-use precinct
Read about the next exciting chapter at Burswood Point as covered in The West Australian.
Watch Burswood Point’s remarkable progress as reported by Nine News.
Golden Sedayu is pleased to share this recent Nine News segment showcasing the exciting progress underway at Burswood Point.
Listen to Golden Sedayu Managing Director on The Perth Property Show
Tune in to hear how we’re building more than homes - we’re building a legacy for Western Australians to enjoy for generations to come.
Over 85 per cent of piling is completed at Somerset
As we move towards crane mobilisation in November, over 85% of the 177 foundation piles have now been tested with 100% pass rate to confirm the strength and integrity of Somerset’s foundations.
DKO Architecture share their insights and inspiration for Somerset
It was wonderful to see future Somerset residents gathered at our Burswood Point Display Suite to hear DKO Architecture share how the exclusive absolute riverfront position at the end point of the Burswood Peninsular informed Somerset’s striking design.