Somerset Burswood Point’s
construction update
At the close of 2025, we are pleased to report that the piling is now 100% complete and that the piling contractor has now demobilised from site. This is a major milestone for the project as Golden Sedayu moves forward with progress on the individual towers.
As we move towards crane mobilisation in November, over 85% of the 177 foundation piles have now been tested with 100% pass rate to confirm the strength and integrity of Somerset’s foundations.
Construction at Burswood Point and Somerset is progressing on multiple fronts, with foundation piling underway, foreshore earthworks and drainage complete, and the boulevard road taking shape — setting the stage for the next phase of development.
Exciting progress is underway at Burswood Point, with foreshore works commencing, the first Garden Homes lots prepped for construction, and activation fill cleared from the Somerset boulevard. Watch the latest video to see the precinct taking shape.
The Golden Sedayu & Golden Sedayu Construction team was pleased to welcome Victoria Park Hon. Hannah Beazley MLA at Burswood Point to view the early progress of Somerset Residences.
Burswood Point continues to take shape, with asphalt works complete, Somerset tower piling underway, and new sewer infrastructure installed – key milestones paving the way for the precinct’s next phase.
One of the major milestones this month was delivery of the piling rig last week and commencement of piling this week.
Somerset at Burswood Point is moving forward, with piling pad construction, dewatering ponds, and deep sewer installation underway.
Burswood Point is progressing steadily, with road subbase construction underway and retaining walls complete.
WA-based developer Golden Sedayu has established its own construction company to deliver luxury residences at the new multi-billion-dollar Burswood Point development.
Burswood Point is moving forward, with road subbase construction and retaining wall works now underway.
Burswood Point is progressing steadily, with sewer backfill and tower site earthworks now complete.